Recently,Dali company-the 100% subsidiary of Eurocrane was rewarded as "2021 First Prize of Excellent Engineering Design in Hydropower Industry"for its' Baihetan cable crane project.
Baihetan Hydropower Station is currently the largest hydropower project under construction in the world with the highest comprehensive technical difficulty. Cable cranes play an important role in material handling between mountains and Dali company was honored to supply seven cable cranes for Baihetan project.
Rely on the excellent design, the seven cable cranes supplied by Dali company have completed more than 30 million tons of materials and equipment handling in total. About 229,800 hours of safe operation and nearly 1 million round trips between mountains has been completed,of which the volume of concrete transferred is around 8.2792 million cubic meters. It has created two world records for the safe operation time among similar machinery and the amount of concrete transportation.